Chronology

Seven Years of Resistance

A timeline of the Pungcheon-ri residents' struggle from 2019 to the present

“Not a single week has been skipped since 2019.”

Scroll sideways to browse the years.

Summer 2019

KHNP Selects Seven Candidate Sites; Hongcheon Applies to Host

Korea Hydro & Nuclear Power selected seven candidate regions for new pumped-storage plants. Hongcheon County applied with Pungcheon-ri as the target area, placing the village directly in the path of large-scale development.

Other
March 2019

Residents File Complaints; County Governor Promises to Stop if Residents Oppose

After learning of the project, residents filed civil complaints. The Hongcheon County governor promised that the project would stop if villagers opposed it, a promise residents say was later broken.

Meetings
April 17, 2019

Hongcheon County Pushes Through Resident Briefing Despite Opposition

Even amid strong local resistance, Hongcheon County went ahead with a public briefing on the pumped-storage project, intensifying distrust among residents.

Meetings
April 19, 2019

Overnight Sit-In and a Second Promise from the Governor

Residents began an overnight sit-in. The county governor again promised to respect residents' wishes, but that promise, too, was not kept.

Protest
Pungcheon-ri residents protesting the pumped-storage plant in 2019Photo source: media report
2019

Residents Form Opposition Committee and Begin Weekly Protests

Villagers formally created the Pungcheon-ri Pumped-Storage Opposition Committee and launched weekly demonstrations, marking the beginning of a struggle that would last more than seven years.

Protest
May 2021

Preferred Developer Selected

A preferred operator for the Hongcheon pumped-storage project was selected, moving the project into a more concrete phase despite local opposition.

Other
February 2022

Public Preliminary Feasibility Review Passes

The project passed a public preliminary feasibility review. Residents criticized the process for failing to properly reflect environmental damage and community opposition.

Legal
August 2022

Youth Direct Action Visits and Joins in Solidarity

Youth climate activists visited Pungcheon-ri and publicly joined the struggle, helping expand its visibility across generations.

Solidarity
2022

Environmental Impact Consultation Completed

The environmental review process was completed, but residents and environmental groups argued that major issues such as forest destruction and wildlife habitat loss were not properly addressed.

Other
May 2023

Planned Project Zone Officially Designated

The planned project zone for the Hongcheon pumped-storage plant was officially designated and announced, escalating residents' opposition.

Legal
October 2023

Gangwon Green Party Issues Official Statement of Opposition

The Gangwon Green Party released an official statement opposing the project and highlighting its environmental and social consequences.

Solidarity
Residents confronting police at Hongcheon County Hall in July 2024Photo source: media report
July 22, 2024

Police Confrontation on the Second Floor of Hongcheon County Hall

Residents faced police inside Hongcheon County Hall, and riot police were deployed. The scene became a symbol of how far the conflict had escalated.

Protest
Pine trees being felled for relocation road constructionPhoto source: media report
October 2024

Logging Begins: 2,256 Pine Trees Cut for Relocation Road

Logging began for the relocation road, affecting 10.96 hectares and 2,256 pine trees before full implementation approval was even issued.

Other
Supporters gathered at the pine forest village event in 2025Photo source: media report
July 12, 2025

Concert and Village Festival Held in the Pine Forest

Residents and supporters gathered in the pine forest for a concert and village festival intended to heal collective wounds and reaffirm solidarity.

Solidarity
August 18, 2025

Daewoo E&C Consortium Selected as Main Contractor

The Daewoo E&C consortium was chosen to build the project, worth 615.5 billion KRW, pushing the conflict into a new phase.

Other
Pungcheon-ri residents at a press conference in front of the planning commissionPhoto source: media report
August 29, 2025

Ministry Issues Implementation Approval Notice

The Ministry of Trade, Industry and Energy officially approved the project, sharpening tensions between residents, authorities, and solidarity groups.

Legal
September 2025

Advance Works Begin on Access and Relocation Roads

After official approval, advance construction began, directly affecting the village and surrounding landscape.

Other
Residents of Pungcheon-ri receiving a civic awardPhoto source: media report
November 2025

Seven Residents in Their 60s to 80s Are Indicted

Seven elderly residents were indicted on charges of refusing to vacate, deepening the human cost of the conflict.

Legal
A solidarity rally marking the 672nd prayer meeting and protestPhoto source: media report
Late 2025

Weekly Protest Count Passes 680

The residents' weekly protest reached more than 680 gatherings, demonstrating extraordinary persistence over more than six years.

Protest
2026년 1월

본공사 착공 예정/주민투쟁으로 연기

홍천 양수발전소 본공사 착공이 예정되었습니다. 84개월간의 대규모 공사가 시작되면 마을과 주변 환경에 돌이킬 수 없는 변화가 시작됩니다. 현재 2026년 7월 까지 연기되었습니다.

Other
2026년 8월 5일

김성환 기후에너지환경부 장관, 주민 대책위 면담서 '공사 강행' 입장

풍천리 주민 대책위가 김성환 기후에너지환경부 장관을 면담했으나, 장관은 사업을 막을 수 없다며 계속 추진하겠다는 입장을 밝혔습니다. 정부가 제시한 근거는 다음과 같습니다. 첫째, 사업 추진 과정에 이렇다 할 법적 하자는 없었다. 둘째, 홍천군·홍천군의회 차원의 의견수렴 과정(주민설명회, 사회단체·주민의 유치 찬성 서명부, 홍천군의회 동의 등)을 거쳤다. 셋째, 반대 의견수렴에 부족함은 있었으나 그 자체로 인허가 절차에 하자가 있었다고 보긴 힘들다. 넷째, 사업 중단 시 약 3,000억 원의 매몰 비용이 발생한다는 점도 백지화를 결정하기 어려운 요인이다. 다섯째, 산림 상태 변경 결정에 산림청이 사실상 동의했다. 7년 넘게 백지화를 요구해온 주민들에게는 사실상의 강행 통보였습니다.

Meetings
As of 2026

The Struggle Continues with Support from More Than 140 Organizations

More than seven years later, the struggle continues. The weekly protest count has passed 705, and over 140 organizations now stand in solidarity with Pungcheon-ri, turning the issue into a national question of ecology, democracy, and residents' rights.

Solidarity
김성환장관 풍천리 방문Photo source: media report
2026년 7월 4일

김성환장관 풍천리 방문

기후부, 한수원에 일시 중지 요청 한 달 간 사업 절차 적정성 검증 김 장관 “주민 초청해 결과 설명” "김 장관은 “경과를 깊이 들여다봐야 할 것 같긴 한데, 처음에 단추가 잘못 끼워진 것 같다”며 “여기는 애초에 안했어야 할 지역같다”고 했다. 이어 “8년 전으로 되돌아가면 안했어야 할 일로 보여진다”며 절차적 정당성을 살피겠다고 했다. "